E-Brick building site in focus (Evere, BE)

08/03/2013

In October 2012, in the town of Evere, renovation work started on 54 social flats using E-Brick. S.C.L. Germinal, a social housing society, is the owner of this building site. The company manages the letting and/or sale of social housing in the outskirts of Brussels.

The building site consists of 6 housing blocks of 9 homes each. At the moment 1 housing block has been finished, i.e. wrapped in E-Brick and jointed. E-Brick allows you to insulate exterior walls of a house or project and simultaneously finish them with facing bricks. This way you will benefit from lower energy bills, a comfortable home and an attractively finished façade in your desired colour.

The main contractor for this project is In Advance. Subcontractor Tadek is installing the E-Brick panels. The left and right side walls are being clad with E-Brick Terra Red, complete with 8 cm PUR. The actual flats will be finished in Terra Red, Yellow Silversand and Mistral, complete with 6 cm PUR.

Project details:
Architect: Franco Soccol
Main contractor: In Advance
Subcontractor E-Brick: Tadek
Supplier building materials: Carimat
E-Brick installation on wooden structure (OSB panels) using wood screws

You can also find the project listed among our completed projects.